Wednesday, May 26, 2010

Clearing Of Debris

Need to use Case Excavator and 2 lorries to remove all construction debris surrounding the house.
Groundbeam for brickwall fencing manual excavation works in progress.

Friday, May 21, 2010

Patio Wooden Panel Ceiling And Plaster Ceiling

Wooden panel ceiling installation in progress.
Plastering works for external columns.
Completed ground beam for brickwall fence. Alamak itu rumah belakang sambung banyak dekat sama border laa. Tak ikut building by law ka? Masa buat tak pikir ke soal pencahayaan, bomba regulation, macamana nak maitenance...?
Living room plaster ceiling works in progress.Plaster ceiling frame works..

Friday, April 30, 2010

Progress Report

Kitchen area completed brickworks and demolished the existing walls.
Roof Covering and bricklaying works completed. Still looking for the design of edge of trusses.
Electrical works running through ceilings at patio.
Completed store room.

Wednesday, April 28, 2010

Store Room Construction


Bricklaying works to the store room in progress.

Tuesday, April 27, 2010

Brickwork In Progress1

Roof covering near completion.
Kitchen bricklaying works completed.
Bathroom in master bedroom.
Electrical wiring works in progress as not to hinder wall plastering works.
Groundslab casting works in progress.

Sunday, April 25, 2010

Main Entrance Door Frame Installation


Additional roof beam for store room area completed. The edge of roof will be joining from front to the store as this will become wrapped around terrace..

Master bedroom bricklaying works completed. To install lintel beam for door opening to the bathroom.
Door frame and bricklaying works to the kitchen door entrance..


Friday, April 23, 2010

Demolition Works

First demoltion work carried out to Bedroom 3 for the adjustment of new window.
Bricklaying works for the new bathroom still in progress.


Bricklaying works for the new Master bedroom.

Wednesday, April 21, 2010

Additional Work For New Store

Excavation for footing and groundbeams for new store (additional works)
Completed roof covering at new patio.
Completed brickwork.

Sunday, April 18, 2010

Brickwork In Progress

Wall and window opening at new living room.
Bricklaying works in action..
Brickwork at new master bathroom..
Brickwork at new master bedroom.

Saturday, April 17, 2010