Demolition Works To The Existing Internal Wall


No electrical conduit pipes?...apa cerita ni...encountered during demolition works to the wall at living room. Ini dah start main wayang punya kerja..nak tergelak pasal kat atas roof beam ada sikit pasang.

Friday, April 30, 2010

Progress Report

Kitchen area completed brickworks and demolished the existing walls.
Roof Covering and bricklaying works completed. Still looking for the design of edge of trusses.
Electrical works running through ceilings at patio.
Completed store room.

Friday, April 23, 2010

Demolition Works

First demoltion work carried out to Bedroom 3 for the adjustment of new window.
Bricklaying works for the new bathroom still in progress.


Bricklaying works for the new Master bedroom.