Showing posts with label excavator. Show all posts
Showing posts with label excavator. Show all posts

Wednesday, May 26, 2010

Clearing Of Debris

Need to use Case Excavator and 2 lorries to remove all construction debris surrounding the house.
Groundbeam for brickwall fencing manual excavation works in progress.

Tuesday, May 18, 2010

Hacking Works And Brickwall Fence

Hacking of existing wall tiles at kitchen area.
Half completed of wash basin table top as per request.
Another rock manual excavation for footing for brickwall fences.
Rock encountered during manual excavation. Besar punya..!

Saturday, May 1, 2010

External New Manhole


Encountered rock during manual excavation for waste water system.

Thursday, April 29, 2010

Existing Manhole At New Master Bedroom Diversion Works

The existing manhole inside the new master bedroom to be removed and install 6" dia. pvc pipe running through under the beams and to be joint with new bathroom..
The Sifu himself fixing the new routing sewerage pipe..

Wednesday, April 21, 2010

Additional Work For New Store

Excavation for footing and groundbeams for new store (additional works)
Completed roof covering at new patio.
Completed brickwork.

Plumbing And Wastewater System


Bathroom Plumbing And Sanitary Works

Manual excavation works for underground wastewater pipe installation works to divert existing sewerage manhole.


Kitchen area excavation works for wastewater and plumbing system installation.

Tuesday, March 23, 2010

Special Column or Tiang

The manual excavation of pad footing for slanting columns. We need another 7 slanting columns in order to make the new extension different from normal house.

Completed roof beam..next will be roof trusses and covering.

Encountered rock or boulders during manual excavation. Slowing a bit the progress of works.

Manual excavation for pad footing for external slanting column at new patio.