Saturday, June 12, 2010

External Fences

Rear brickwall fence completed works.

Completed column for fencing work.
Formwork and rebar fixing works to fences structure.

Tuesday, May 4, 2010

Proposed Light Fittings To Patio


Light fittings to external slanting columns....kalau nak laaa..harga rm 90.00 1 bijik..
Plastering works started today.

Tuesday, March 30, 2010

Roof Trusses

Slanting column at new patio completed...next roof beam..


Taking down existing roof covering
The existing roof tiles temporarily taken down for new trusses construction.

Sunday, March 28, 2010

Reinforced Concrete For Slanting Columns

Concreting works in progress for another 2 columns.




Completed r.c column, next roof beam for new patio...

Saturday, March 27, 2010

Tuesday, March 23, 2010

Special Column or Tiang

The manual excavation of pad footing for slanting columns. We need another 7 slanting columns in order to make the new extension different from normal house.

Completed roof beam..next will be roof trusses and covering.

Encountered rock or boulders during manual excavation. Slowing a bit the progress of works.

Manual excavation for pad footing for external slanting column at new patio.

Tuesday, March 16, 2010

Kerja-kerja Struktur

Kerja pembinaan column and roof beam sedang giat dijalankan..